A102/A201 | Scope of Work | Name the Exhibit | Insurance and Rates | Executing the Work |
---|---|---|---|---|
What is green.
The color that shall be used by contractor to markup submittals.
|
What is Exhibit C.
The contract Exhibit defining the scope of work.
|
What is the Exhibit A.
Contract Documents - Drawings, Specs and Reference Documents
|
What is Exhibit C-1.
Where contract labor rates are defined.
|
What is daily.
The frequency that graffiti and posters on barricades and fences shall be removed.
|
With advanced written approval from Ownership.
When cost for promotional lunches, parties, jackets, t-shirts, etc is allowable?
|
What is 2 years.
The duration of the project’s minimum warranty for all Work (unless specifically noted/spec’d otherwise)?
|
What is the Exhibit G
Schedule of Unit Prices
|
What is the total value of subcontracts included into the program.
The Subguard Program is charged to the Owner at a rate of $12.09/$1,000 of this value.
|
What is Schedule I Q&E Site Logistics Plan
Contractors General Conditions includes the perimeter fencing, closures and roadways as shown where?
|
What is 10 days.
Contractor shall respond to Change Order requests as soon as reasonably possible, but not later than ____ days?
|
What is True.
If subcontractor’s proposal includes unusual OT or shift work to achieve the Schedule, the owner may elect to extend the Schedule, or pay for such OT or shiftwork, but the Contractor shall not receive any adjustment to GC’s or Fee. (T or F)
|
What is the Exhibit H
Qualifications and Exclusions
|
What is $21.00/$1,000 of enrolled subcontracts
The rate the CCIP is charged to the Owner.
|
What is Sprinkler/Standpipe Systems
This system requires Pre-Installation Drawings, Calcs, and Cut-sheets per the Risk Control – Construction Design Guidelines
|
What is 100% of fee.
CHDJV's liability due to delays shall not exceed this amount.
|
What is 14 days.
The number of days the contractor has to give complete pricing for all changes to the Work upon receipt of change request documentation for such pricing.
|
What is the Exhibit U
Insurance Rates
|
What is $40 MM.
The subcontract value wherein Zurich's pre-qualification is required for the Subguard program.
|
What is 1 day.
The required notice the Contractor must provide before seeking approval for any proposed allocation of Contingency in excess of $25,000.
|
What is litigation in a court of competent jurisdiction.
The method for binding dispute resolution?
|
What is 5 days.
The number of days the Contractor has to submit a completed FAA Form 7460-2 after construction reaches its greatest height?
|
Varies by Subcontract until GMP
Current Contract Drawings
|
Who is anyone CHDJV desires.
Parties excluded by the CCIP are:
a) surveyors b) consultants c) parties who merely transport d) _________? |
What is all of the above.
The Contractor may bill for off-site stored materials if which of the following requirements is met:
a) material has a long lead time and delivery to site can’t be guaranteed otherwise b) it is clearly identified for this project c) Notice of intent to bi |